Tapertube testing at JFK
The Development of the TAPERTUBE ™ PILE
By John J. Dougherty, DFP Foundation Products, LLC
 
Tapertube cast steel connical tip
Tapertube cast steel pointThe advantages of a tapered shape for a pile have been known for many years.  Some soil conditions that would otherwise not carry much load using a straight-sided pile will carry a substantially higher load when the pile is tapered.  The combination of bearing and frictional resistance produced by the wedge shape of the taper is greater than the side friction and end bearing of a cylindrical pile.

Timber piles were the first tapered piles.  Perhaps the designer of the tree engineered the shape of the trunk with piles in mind.  Using the trunk as a pile must have come easily to ancient pile drivers; placing the small end down was obviously a better way to drive a tree trunk into the ground.
 

Junttan pile driver lifting a Tapertube
Junttan pile driver lifting a TapertubeThe TAPERTUBE is extended to the required project length using standard size steel pipe.  The end of the TAPERTUBE that is to be spliced to the pipe is rounded to match the diameter of the pipe.  This important step in the process, allows a smooth full strength joint that does not break the friction between the pile and the soil.  The splicing would usually be done off site before the piles are shipped to the jobsite in lengths up to eighty feet (80’).  If additional lengths must be added at the job, a product such as the DFP S-1800 drive fit splice or a field butt weld can be used.

 

The Port Authority of New York and New Jersey reviews all work to be done at JFK.  They have approved the TAPERTUBE pile for use.  They have stated in a letter, “We have reviewed the performance of the TAPERTUBE piling driven for JFK-LRS (light rail system) pile test program and the production and test piles driven for the British Airways Project.  The piling performed exceptionally well during both pile driving and load testing and meets our requirements for tapered pile applications.  We will be including the TAPERTUBE pile as an acceptable alternative on our future projects and will accept them for tenant projects as well.”

Tapertube ready for installation

Tapertube ready for installationEngineers today, are striving to increase pile loads in order to reduce the number of piles used.  Until the development of the TAPERTUBE pile, this was difficult for tapered friction piles.  The alternative tapered pile, although fluted to add some stiffness, is manufactured in gage thickness only with the heaviest metal being three- gage (3) or (0.239”).  The TAPERTUBE, depending on tip size, can be made in wall thickness up to one-half inch (0.500”).

 

Listed below are results of TAPERTUBE pile compression, lateral and uplift tests performed to date at JFK Airport.  TAPERTUBE piles being driven at JFK have a tapered lower section that is twenty-five (25’) feet long which is fabricated using 0.312-inch thick steel plate (50ksi yield). The twelve-sided (12) cross-section is eight- inch (8”) diameter at the bottom and eighteen-inch (18”) diameter at the top.  A length of eighteen-inch (18”) diameter 0.375” wall, ASTM A-252 grade 3 pipe (45 ksi yield), is fully butt-welded to the rounded top of the TAPERTUBE. After installation the pile is filled with five ksi (5) concrete.

Dynamic testing of Tapertube
Dynamic testing of TapertubeThe piles are being driven with a Junttan HHK-7 hydraulic hammer with a 15000- pound ram and a delivered energy (per PDA measurements) of about 45000 ft.-lbs.  Final driving resistance for pile design capacities ranging from one hundred-twenty (120) tons to one hundred-eighty (180) tons have been reduced to seventeen (17) to twenty-five (25) blows per foot after the initial compression load tests, driven to higher resistances, indicated that the requisite capacities would be achieved at lower driving resistances.  Load tests are started no sooner than twenty-one (21) days after driving and generally show increases in ultimate compressive capacity of twenty-five (25) percent or more over the PDA measurements made at the time of driving.  The soil profiles for the various sites at JFK are relatively uniform, and consist typically of five (5’) to fifteen (15’) feet of sand fill, zero (0’) to five feet (5’) of peat or organic silt, and underlain by medium to fine sand having “N” values typically ranging from ten (10) to thirty (30) blows per foot to depths of one hundred feet (100’) and more.  The water table is generally at a depth of ten (10’) to fifteen (15’) feet. Potential liquefaction due to seismic considerations has mandated minimum pile lengths of about forty-five feet (45’).

 

A summary of some of the load tests are shown below:
 
 

                        COMPRESSION TESTS
 
SITE
PILE NO.
PILE LENGTH (FT)
FINAL BLOWS/ FT.
DESIGN CAP
(TONS)
MAX. PDA
CAP
(TONS)
ULT. CAP. TEST (TONS)
LIGHT RAIL SYSTEM
OMSF 10
52
41
150
315
>425
 
CTA 10
64
25
150
283
425
BRITISH AIRWAYS
L2M-P3
59
18
120
300
375
 
L4M-P27
45
50
150
375
>390
 
L4M-P28
50
28
150
368
>375
 
COL25-#66
55
20
150
275
380
ARRIVALS BUILDING
#1239
58
21
180
275
>430

 

                        LATERAL TESTS
 
SITE
PILE NO.
PILE LENGTH (FT)
FINAL BLOWS/FT.
FINAL LATERAL TEST LOAD (TONS)
DEFL. @ FINAL LOAD (IN)
LIGHT RAIL SYSTEM
CTA-9
64
25
25
<.4
BRITISH AIRWAYS
COL 25-#552
60
22
25
0.8
ARRIVALS BUILDING
1239
60
21
18
.4

 

                        UPLIFT TESTS
 
SITE
PILE NO.
PILE LENGTH (FT)
FINAL BLOWS/FT.
FINAL UPLIFT TEST LOAD (TONS)
DEFL. @ FINAL LOAD (IN)
LIGHT RAIL SYSTEM
OMSF 3
65
40
44
<.07
 
FED CIRC 13
60
33
50
<.06
BRITISH AIRWAYS
COL 22-#124
45
21
100
0.1
 
COL 13-#372
45
20
100
0.1
ARRIVALS BUILDING
#1243
58
24
100
<.18

 

DFI members participating in this work are Stan Merjan of Underpinning and Foundation Constructors, Inc., George Tamaro and Joel Moskowitz of Mueser Rutledge Consultants, Skyline Steel, and Jack Dougherty of DFP Sales, Slattery Associates, GZA-Raamot Associates, and Mel Esrig, Consultant.
 

More information about TAPERTUBE is available by calling John Dougherty at 201-337-5748, or email john@tapertube.com if you prefer.

© Copyright 2001 - 2023 Pileline Publishing

Back to Pileline Online Electonic Magazine

Back to Pileline Online's Home Page